DLF One Midtown construction update
CONSTRUCTION STATUS OF TOWER A, B, C AND D OF DLF ONE MIDTOWN MOTI NAGAR BY FAR!!!
Tower A - 30th floor
DLF One Midtown Tower A is completed over the 30th floor and roughly 9 floors are left where the rapid construction will complete this tower soon.
Tower B - 34th floor
Whereas tower B is completed till 34th floor and rest are in the pipeline where the tower B east and tower B south will be finished on its estimated time.
Tower C - 33th floor
Tower C east and west is finished till the 33th floor and the finishing part will be the next target.
Tower D - 30th floor
This tower is ready by 30th floor and aggressive work will move it to its completion stage.